1.2.3 Installing the Main Body Unit
[Fix the hoisting stand firmly]
Water level
(1) Install the hoisting stand on the hoisting screw by using nuts and gaskets at both the upper and
lower sides of the hoisting stand. To prevent the gasket from breaking off, a gasket anchor board can be
helpful.
(2) Install the paper template on the unit, and fix the drain pipe at the outlet vent.
(3) Adjust the unit to the best position.
(4) Check if the unit is installed horizontally at four directions. If not, the water pump and the float
switch would function improperly and even lead to water leakage.
(5) Remove the gasket anchor board and tighten the nut remained.
(6) Remove the paper template.
≥1500mm
(59inch)
Figure 3-1-24
Table 3-1-5
Models
GKH24S3GI
GKH36S3GI
GKH42S3GI
GKH48S3GI
Nut(field supplied)
Gas(attachment)
Hoisting stand
Tighten(double nuts)
Center of the ceiling
opening
Polyethylene pipe
Figure 3-1-39
U-Match Series DC Inverter Service Manual
H
≥1500mm
(59inch)
H
mm (inch)
260(10-1/4)
340(13-3/8)
340(13-3/8)
320(12-5/8)
Insert
Gasket anchor board(attachment)
[Fix the gasket firmly]
One bolt located at one corner of the outlet pipe
should be fixed on one corner of the drainage slot.
Bolt(attachment) [Fix the paper template]
61
paper template
Bolt(attachment)