After the completion of the positioning and the stabilisation phases have the platform control panel
3
inserted back into its docking station in the cage.
If there is the radio control unit make sure that micro-magnetic switch placed on the side

Moving the aerial part

Make sure that the load conforms to the originally set limits and is
well distributed around
Make sure that the bar closing access to the platform is properly
secured
Make sure that the red emergency stop button is not pressed down
neither on the ground control panel nor on the platform control panel
Always check that the warning emergency lights are not lit up
indicating some sort of emergency situation
Lifting of the boom is the first operation to be executed in order to commence the
By lifting the boom above 5°, all the movements of the aerial part are activated.
of the platform control panel is securely pushed into its socket.
activation of the lifting system
A
B
82
IM R13 T
3
Push forward the S6
Lift the boom by pushing forward
the M2 joystick