Replace a Boot Drive in the Verde 4U Master Node
Power Off the Array
The nTier Verde array must be powered off before replacing a boot drive.
Use the following instructions to power off the array.
1. Click the power icon in the lower right‐hand corner of any screen in the
2. On the Power screen, click Shutdown.
3. A confirmation screen displays. Confirm the selection to shutdown the
4. Once the array finishes powering off, disconnect the power cords from
Disconnecting the power cords is necessary to take the array out of Standby power
Caution
mode. While in Standby, the motherboard can be damaged by a dropped screw or
electrostatic discharge.
5. Disconnect all Ethernet and SAS cables from the array. It may be helpful
October 2013
StrataView web interface. The Power screen displays.
Figure 3 The Power icon.
nTier Verde array.
the power supplies.
to label the cables to ensure they are re‐connected to the correct port at
the end of the procedure.
Boot Drive Replacement—Spectra nTier Verde Array
Power Off the Array
Power icon