3.3 Installation Process

Remove the protective plastic bag from the cabinet only immediately before
installation. Do not remove the bag during equipment room renovation or
infrastructure construction; otherwise, dust may enter the cabinet and affect the
internal components.
Figure 3-15 Installation flowchart

3.4 Checking the Nitrogen Pressure

Context
Procedure
Step 1 Open the door lock using a key, and open the cabinet rear door.
Issue 04 (2021-03-15)
NO TICE
The device has been injected with 0.2–0.6 MPa nitrogen before delivery. Check
the nitrogen pressure for nitrogen leakage.
You can open or close the exhaust valve using a flat-head screwdriver.