Blower Motor Check
• The following procedure must be completed by a qualified service person after the installation of
the PROCESSOR is complete.
• For this procedure all ACCESS PANELS including the TOP COVER must be removed from the
PROCESSOR. See Figures ?? through ?? on page ?? for ACCESS PANEL locations.
[1]
Remove the BLOWER MOTOR COVER. Check that the BLOWER MOTOR and BELT are in the correct
position for 50 Hz or 60 Hz operation.
40
System Check-Out
IMPORTANT
BLOWER MOTOR
BELT
60 Hz (Factory Set)
Figure 46
50 and 60 Hz Blower Motor Operation
50 Hz
H108_0358BCA
H108_0358BA
1C0932