Commissioning | Automax 100 | Basic module TS-AC B1-M2-1X
Commissioning
Preparation for commissioning
Proper commissioning requires that:
The delivery, the transport and the unpacking according to chapter
product" as of page [25] and chapter
been properly completed
Proper completion of assembly including electrical connection according to chapter
„Assembling the
product" as of page [29]
All parts required are within reach and functional
8.1
First commissioning
Compromising of the training system, individual components or other assets. Risk
for safe operation of the training system!
Risk of injury or death for operator or third
Chapter
„Safety
instructions" as of page [7] in these operating instructions must
always be observed!
High electrical voltage!
Danger to life, risk of injury by electric shock.
Defective or damaged components or cables must be replaced. This also applies for
the required power supply units and their connection cables
Do not open any covers or device sockets during operation
Do not separate or connect plug-in connectors when energized
Risk of tripping and falling!
Risk of tripping and falling due to incorrect routing of mains connection cables
Do not route cables through passage areas
Use cable bridges for routing of mains connection cables on the floor
Do not tension the mains connection cable
If necessary, use an extension cable with respective cross-section
If a DC 24 V power supply unit with low output current is used, the basic module cannot be
operated up to its performance limit.
ATTENTION! The required output current to be provided by the power supply unit is
calculated from the total maximum current consumption of:
Basic module
Extension module
Sensors
Actuators
„Unboxing the
DANGER
DANGER
CAUTION
Bosch Rexroth AG | 04.2021 | DOK-SUPPL*-TS-AC B1-M2-ITRS-EN-P
„Transporting the
product" as of chapter [27] have
31/54