Rack Mount Installation

The ATP-2000 can be mounted into a 19 inch rack. It requires 2RU of vertical space in a desk-
mount or full-rack system:
1 Select an equipment rack location with a nearby AC power socket.
2 Install the DC Power Supply Module into the rack.
3 Locate the ATP-2000 unit in the rack.
Fig. 2-1: Rear Air Venting Grilles
4 Secure the ATP-2000 unit in the rack with four M6 screws and washers. Fasten it to
captive nuts of the rack frame mounting strip. See Figure 2-2.
4 Screws
(Typically M6 x 12),
with plain washers or cups.
Fig. 2-2: ATP-2000 Rack Mounting
CAUTION
Support the body of the DC Power Supply Module.
Do not let it hang by any electrical cords.
CAUTION
Allow 50 mm (approximately 2 inches) clearance at the rear of the ATP-
2000 for unit cooling airflow, mating connectors and cables.
Note: See Environmental, on page 49 in Appendix A, for information about
the ATP-2000 unit's operating temperature range.
GV label
Air Venting Grilles
ATP-2000
User Guide
7