Application Turnover Check List; Software Configuration Checks - GE Vivid T8 Basic Service Manual

Hide thumbs Also See for Vivid T8:
Table of Contents

Advertisement

Application Turnover Check List

Software Configuration Checks

Step
1
Verify Date and Time is correct.
2
Verify that Location (Hospital Name) is correct.
3
Verify Language settings are correct.
4
Verify assignment of Print Keys.
5
Verify all of the customer's options are set up
correctly.
Vivid T8/ Vivid T8 Pro – Basic Service Manual
5490863-100 English Rev. 03
Complete these checks before returning the scanner to
customer for use:
Table 4-4:
Software Configuration Checks
Task to do
Application Turnover Check List
Notes
Demo Option strings turn on
4-37

Advertisement

Table of Contents
loading

Table of Contents