4.4 Place of installation

4.4.1 UPS location

Note!
UPS installation and connection must be performed only by an ABB Service Technician!
If optional cabinets and accessories are included with the UPS, please refer to those accompanying
manuals for installation and operating instructions.
The UPS is intended for use in electrical rooms.
Do not locate or stock easily flammable materials in the same room as the UPS.
It is important to have a clean, dust-free environment provided with proper ventilation and air-conditioning to
keep the ambient temperature within the specified operating range.
The recommended air inlet temperature is from 68°F (20°C) to 77°F (25°C) (max. 104°F / 40°C).
Refer to Section 4.5.
Check for sufficient floor load capacity before installing the UPS and the Battery.
Refer to Section 4.1.1.
For Battery installation follow the local codes and the recommendation of the Battery supplier.
Note!
Operation at temperatures higher than 77°F (25°C) will reduce Battery life.
Potential consequences are explained in the User Manual to Section 9.1.4: read and understand
them.
The TLE Series 625 to 1000 UPS can radiate radio frequency energy.
Although some RFI (Radio Frequency Interference) filtering is inherent to the UPS there is no guarantee that the
UPS will not influence sensitive devices such as cameras and monitors that are positioned close by.
If interference is expected, the UPS should be moved away from the sensitive equipment.
Positioning of the UPS TLE Series 625 to 1000
Min.
20" / 500mm
TLE Series 625 & 750
Fig. 4.4.1-1 TLE Series 625 to 1000 - Positioning of the UPS
TLE Series 625 to 1000 PurePulse™ UL S2
Min.
20" / 500mm
TLE Series 1000
UPS Installation Guide / REV-B
The rear panel of the UPS may be
mounted flush to a wall or other
structure.
Clearance around the front of the unit
should be sufficient to enable free
passage of personnel with the doors
fully open, and to allow sufficient
airflow to the door vents.
Check Section 110-26(A) of the NEC
code for specific requirements.
To
guarantee
proper
exhaust,
the
mandatory
clearance between ceiling and top of
the UPS is 20" (500 mm).
A single-phase power outlet (120Vac)
should be provided near the UPS for
connection
of
power
equipment or connectivity devices.
This outlet must be grounded.
cooling
air
minimum
tools,
test

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tle 750 seriesTle 1000 series

Table of Contents