Figure 3-11 Removing plugs
Step 7 Insert four M12x115 expansion bolts into the expansion bolt holes in the floor,
and tighten the expansion bolts in the direction.
Figure 3-12 Tightening expansion bolts
----End
Unsecured Installation
Step 1 Adjust the four anchor bolts at the bottom of the UPS cabinet until all the four
castors at the bottom hang in the air and the anchor bolts bear all of the cabinet
weight, as shown in
Issue 11 (2020-12-07)
Figure
3-13.