Functions
9.1 Calibrating
9.1.3

Calibration of ULTRAMAT 6/OXYMAT 6

The Set CEM CERT system is configured so that the ULTRAMAT 6 analyzer
automatically performs an AUTOCAL (here: zero and full-scale value calibration) with
the permanently connected zero and calibration gases once per week. The timing for this
can be set.
The OXYMAT 6 can be operated in the same way as the ULTRAMAT 6 described here.
9.1.3.1
ULTRAMAT 6 – AUTOCAL calibration of the zero point and full-scale value
If the ULTRAMAT 6 has two measurement channels, these are calibrated at the same
time with one calibration gas during an AUTOCAL. In the case of two calibration gases,
the calibration must be adapted appropriately so that the measurement channels are
calibrated one after the other in the AUTOCAL sequence.
A complete AUTOCAL is performed with the operating sequence "Menu" → "Calibration
U6" → "Start AutoCal". The status traffic light is orange while the calibration takes place.