Application planning

4.1

Transport

Proper transport, storage, setup and installation, as well as careful operation and
maintenance, are essential for the error-free, safe and reliable operation of this system.
In particular, both the general erection and safety regulations governing work on
electrical power installations (e.g. DIN, VDE) and the regulations governing professional
use of lifting equipment and machinery and the use of personal protective gear (safety
glasses, etc.) must be observed.
The lifting eyes/transport shackles on the roof of the analysis cabinet must be used for
transporting the cabinet.
The analysis cabinet should be mounted and secured to prevent it from falling over
immediately after transport.
4.2

Checking the delivery

Each analysis cabinet is individually configured. Therefore, you should check the delivery
for completeness (correspondence with packing slip) before installation.
In the case of transport damage that can be attributed to improper handling, arrange for
a damage assessment by the shipping agent within 7 days.
Also check the following:
• Are the surfaces of the system and its components clean and undamaged?
• Have any lines been loosened after transport?