Powering On The System - Mitsubishi Electric AnyWire NZ2AW1C2AL User Manual

Cc-link-anywireaslink bridge module
Table of Contents

Advertisement

4.6

Powering on the System

After checking the items described above, power on and start the system.
How to power on the AnyWireASLINK system is as follows.
The order is inverted when the system is powered off.
1.
24VDC external power supply for the AnyWireASLINK system
(This step is required only when the supply power of slave module is different from power supply of the bridge module. When
the supply power is same as the bridge module, this step is not required.)
2.
Power supply of the bridge module
3.
Power supply of the programmable controller
24VDC external power supply
(for slave module)
Power supply of the bridge
module
Power supply of the
programmable controller
Remote READY
Sequence program
• Supply the power according to the steps; 1) 24VDC external power supply of AnyWireASLINK system, 2)
the bridge module, 3) the programmable controller, or turn on them at the same time.
• If the bridge module is powered on before the 24VDC external power supply in the AnyWireASLINK system,
a transmission cable voltage drop detection error may occur.
• After Remote READY (RX(n+1)B, RX(n+3)B, RX(n+5)B, RX(n+7)B, RX(n+D)B) turns on, wait at least one
second to start the sequence program.
4 CONNECTIONS
36
4.6 Powering on the System
ON
OFF
ON
OFF
ON
OFF
ON
OFF
1 second
or longer