Sample Schedule for Installation
PN: 1725-36096-001_J.doc
This schedule assumes that the facility has been completely prepared
for the installation and that all Base Station mounting follows
Polycom standards. For larger installations (greater than 18 Base
Stations), the schedule may be lengthened.
Day one
The Polycom field service engineer will install the system and train an
administrator. Our engineer will usually be on-site from 9 a.m. to
5 p.m. Activities will include the following:
When the Polycom field service engineer arrives on-site he/she will:
1. Survey site for installation preparation.
2. Inventory equipment.
3. Set up MCU and verify operation.
4. Register, label and verify operation of all handsets.
5. Program any feature codes required.
6. Install Base Stations and verify operation (see note below).
7. Test coverage of system and make any required adjustments.
8. Install and verify modem connection.
9. Provide system administrator with coverage map.
10. Walk the site with the system administrator to show coverage.
11. Train the system administrator(s).
Polycom standard mounting is on 7/8" T-bar grid or on 3/4" steel
beams. All areas must be accessible with standard on-site
equipment. All other non-standard or non-accessible mounting of
the Base Stations should be completed by the customer prior to
the Polycom installation.