Note: The floor will be flipped over and
floor runners will sit on your foundation.
It is important to note that having a
level foundation is critical. Choosing a
foundation will vary between regions.
Typical foundations can be concrete
pads or patio stones positioned
underneath the floor runners.
centered on
floor frame.
10.
Position Plywood Floor pieces (4) on top of completed
floor joists. Plywood will sit slightly back from outside edge of
Floor Joist Framing.
11.
When in correct position, attach with 1 1/4" screws. Use
screws every 16". The Plywood is cut slightly smaller than floor
framing. Keep plywood seams tight.
12.
Place remaining 71 3/4" Floor Joist and 18" Short Floor Joist in
floor cavity. Attach to floor frame with 4 - 2 1/2" screws for the long joist
and 2 - 2 1/2" screws for the short joist. These extra joists will make a
larger attachment surface for the patio deck boards in Step 24.
Toll Free 1-888-658-1658
9.
With Floor Runners
attached, carefully flip
the floor over and place
on
your
foundation.
Caution: you will need 2
people to assist you. Be
careful when laying floor
down not to bend or twist
it. When in place, level
floor completely.
www.outdoorlivingtoday.com
Page 7
Concrete Slab
Foundation
plywood
pushed together
at seam.
Hint: Use a chalk line
to mark location of floor
joists
screw placement.
Important: Make sure floor
is level before moving on
to wall section. Use a level
to confirm and shim floor
joists as required.