Table 3-5 Post-installation check items
No.
1
2
3
4
5
6
7
Issue 07 (2020-01-10)
Item
Cable routing
Cable connections
Cable connections for USB ports
and network ports
Cable labels
Ground cable connection
Distances between cable ties
Operating environment
Copyright © Huawei Technologies Co., Ltd.
Expected Result
Cable routing meets engineering
requirements.
Power cables and battery cables are
tightened to specified torques using a torque
wrench, connected correctly, and free of
damage.
Cables to USB ports and network ports are
connected correctly and securely.
Labels are neatly attached to both ends of
each cable, and the information on the labels
is concise and understandable.
The ground cable is securely connected to
the equipment room ground bar. Measure
the resistance between the UPS ground
cable and the equipment room ground bar,
which must be less than 0.1 ohm.
Distances between cable ties are the same,
and no burr exists.
Clean the conductive air and other sundries.