5. Install the four provided legs and set up on a level surface, preferably concrete.
When all four legs are mounted in the same pin hole, the seed treater has a slight
slope to allow seed to travel through the machine. The pin holes are approximately
2" apart.
If more slope is desired, the rear legs can be dropped an additional pin
hole.
6. Anchor the seed treater in position to prevent the machine from moving during
operation.
7. Inspect machine thoroughly for screws, bolts, fittings, etc. which may have come
loose during shipping.
8. The pump stand(s) should be placed on level ground close to the seed treater.
9. Attach the chemical tubing from the pump stands(s) to the atomizer plumbing on the
seed treater (below left). Additional tubing can be added or removed to
accommodate your set-up.
10. Setup the automated main control panel at a place that is convenient to the
operator. This may include attaching the automated main control panel to the seed
treater, to the wall or to the control panel stand that will require anchoring.
11. Connect the gray cable with light blue ends to one of PJCAN connections on the
bottoms of both the treater and automated control panels. Connect the two light
blue plugs into each of the remaining open PJCAN connections.
12. Connect the red cable to the PJESTOPA on the treater control panel and then to the
PJESTOPB on the automated control panel. This cable must run from an A
connection to a B connection (never A o A). Connect the two red plugs into each of
the remaining open PJESTOP connections.