TO START SPECIAL CYCLES...
1. On the SPECIAL CYCLE MENU screen, select a
cycle, and press
to validate.
2. Press Start
to start the cycle.
3. To stop the current cycle press Reset
PARAMETERS menu
Use this menu to configure the measurement cycle associated to each test program.
PARAM / Pr 001
TYPE : LEAK TEST
COUPL. A
FILL TIME
STAB TIME
TEST TIME
DUMP TIME
Press. UNIT
Max FILL
Default parameters of the LEAK type tests
Label
Parameter
COUPL. A or COUPL. B
Coupling time
FILL TIME
Fill time
STAB TIME
Stabilization time
TEST TIME
Test time
DUMP TIME
Dump time
Press. UNIT
Pressure units
Max FILL
Maximum fill pressure
Min FILL
Minimum fill pressure
LeakUnit
Reject unit
Test FAIL
Test fail
Ref. FAIL
Reference fail
FUNCTIONS
Functions
Some parameters are displayed when specific functions are activated.
Label
Parameter
INTER-CYCLE
Inter cycle time
Max PreFILL
Max pre fill pressure
OFFSET
Leak offset
PRE DUMP
Pre dump time
QSG_F620.283.00_EN_01 / 2019-02-20
.
0.0 s
2.0 s
2.0 s
2.0 s
1.0 s
bar
5.00
Description
Required times when instrument manage
automatic jigs
Time to pressurise the part under test
Time to stabilise the pressure on the test and
reference parts
Time for leak measurement
Time to vent the part to atmosphere
Pressure unit (bar, mbar, PSI, Pa, kPa, MPa)
Maximum level of the fill pressure
Minimum level of the fill pressure
Measurement units
Upper leak rate limit for the test part. Above this
limit, the part is considered as defective.
Reference part reject level
Access to additional functions
Description
Time between two automatically chained
programs (Sequence function)
Maximum level of the pre fill pressure (Pre fill
function)
Leak offset value
Time to dump the part under test (Pre fill
function)
39 / 46