Parameterization With The Bop (Two Examples) - Siemens SINAMICS G120 Operating Instructions Manual

Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

4.6.3

Parameterization with the BOP (two examples)

All of the parameter changes, which are made using the BOP, are saved so that they are
protected against power failure.
Changing a parameter value using the BOP
The following description is an example of how to change any parameter using the BOP.
Table 4- 5
1
2
3
4
5
6
Using the BOP to change parameters with more than one index
The next example shows how the value of an indexed parameter can be changed.
Table 4- 6
1
2
3
4
5
6
7
8
9
Note
When parameter values are being changed, the BOP sometimes displays the message
"bUSY". This means that the inverter is currently processing a higher-priority task.
CU240S and CU240E Control Units, FW 3.2
Operating Instructions, 03/2009, A5E02440075B AA
Change P0003 (set user access level "3")
Step
Press
to access the parameters.
Press
until P0003 is displayed.
Press
to display the parameter value.
Press
or
to set the required value (to 3).
Press
to confirm and save the value.
The user can now view all parameters in steps 1 to 3.
Change index parameter P0700 (set command source "BOP" under index 1)
Step
Press
to access the parameters.
Press
as often or as long as required until P0700 is displayed.
Press
: index "in000" is displayed.
Press
or
to select index 1.
Press
to display the value that is currently set.
Press
or
until the required value is displayed.
Press
to confirm and save the value.
Press
until r0000 is displayed.
Press
to reset the display to the standard drive display (as
defined by the customer).
4.6 Commissioning with the operator panel
Result displayed
Result displayed
Commissioning
73

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cu240s pnCu240s pn-fCu240eCu240sCu240s dpCu240s dp-f

Table of Contents