4.5.1

Creating a STARTER project

Description
An inverter can be parameterized in a user-friendly fashion using the Project Wizard. The
commissioning procedure described here follows the Project Wizard. The PC communicates
with the inverter via the USS interface.
● Switch on the inverter supply voltage
● Launch the STARTER commissioning tool.
● Use the Project Wizard and click on the "Find drive units online ..."
● In the screen that follows (not shown here), enter a meaningful name into your project,
● Click "Change and test..." to set up the PG/PC interface.
CU240S and CU240E Control Units, FW 3.2
Operating Instructions, 03/2009, A5E02440075B AA
Figure 4-4
Start field
e.g. "Basic Commissioning" and click on "Continue". The following dialog box is
displayed.
Figure 4-5
Setting the PC interface
Commissioning
4.5 Commissioning with STARTER
59