B R A V O ™ 8 1 0 5 M A C H I N E I N S T A L L A T I O N
2
Facility Utility Connections
Facility Utility Connections
Introduction
Setup
Photograph
2-38
Bravo™ 8105 Nitrogen version machine requires chilled water and nitrogen
connections provided from the facility. If chilled water is not available, a separate
water chiller must be used. The Coolant In and Coolant Out connections are
located at the Unload End of the machine on the upper portion of the frame. The
Nitrogen connection is located between the third and fourth rear panels on the
lower frame.
The ½ in. FNPT fittings are pretreated at the factory with teflon tape. To connect
the facility hoses to the connector, simply place the hose on the hose barb and
tignten with a hose clamp. Refer to Figure 2–15.
Figure 2–15
Bravo™ 8105 Installation Guide
Rev. 2