Procedure
Step 1 Push the locking latch towards the left.
Step 2 Pull the handle outwards and remove the SMU, as shown in Figure 4-3.
Figure 4-3 Removing an SMU
Step 3 Insert the new SMU into the subrack, push the locking latch towards the left, and pull out the
handle.
Step 4 Slide the SMU into the subrack slowly along the guide rails, push in the handle, and then push
the locking latch towards the right.
Step 5 Reset the parameters on the SMU.
Figure 4-4 Installing an SMU
----End
Follow-up Procedure
Pack the removed component and send it to the local Huawei warehouse.
4.4.3 Replacing an AC SPD
Prerequisites
Issue 03 (2019-11-15)
An ESD wrist strap, ESD gloves, ESD box or bag, required tools, and cabinet door key
are available.
The new AC SPD is intact and the indication window is green.