First Commissioning; Warming Up The Machine - Optimum OPTIdrill RD 5 Operating Manual

Radial drilling machine
Table of Contents

Advertisement

OPTIMUM
M A S C H I N E N - G E R M A N Y
ATTENTION!
Ensure that all 3 phases (L1, L2, L3) and the ground wire are connected correctly.
The neutral conductor (N) of its power supply is not connected.
ATTENTION!
Make sure that the direction of rotation of the drive motor is correct. The switch position
of the rotation selector switch for right-handed rotation (R) has to turn the drill spindle
clockwise. If necessary, exchange two phase connections.
The automatic spindle sleeve feed moves in the wrong direction and components may
be damaged when it reaches the end stop.
The guarantee will become null and void if the machine is connected incorrectly.
3.11

First commissioning

The machine may only be commissioned after proper installation.
ATTENTION!
Before initially operating the machine, check all screws, fixtures and/or safety devices,
and tighten up the screws if necessary!
WARNING!
The use of improper tool holders or their operation at inadmissible speeds constitutes a
hazard.
Only use the tool holders (e.g. drill chuck) which were delivered with the machine or
which are offered as optional equipment by OPTIMUM.
Only use tool holders in the intended admissible speed range.
Tool holders may only be modified in compliance with the recommendation of OPTI-
MUM or of the manufacturer of the clamping devices.
WARNING!
When first commissioning the radial drilling machine by inexperienced personnel you
endanger people, the machine and the equipment.
We do not assume any liability for damages caused by incorrectly performed
commissioning.

„Qualification of personnel" auf Seite 11

3.11.1 Warming up the machine

ATTENTION!
If the radial drilling machine and in particular the drilling spindle is immediately operated
at maximum load when it is cold, it may result in damages.
If the machine is cold, e.g. directly after having transported the machine, it should be warmed
up at a spindle speed of only 500 rpm for the first 30 minutes.
GB
RD5
Assembly
Page 34
Original operating instructions
Version 1.0
2017-03-13