Please observe the following points:
The machine must only be installed and operated in a dry and well-ventilated place.
Avoid places near machines generating chips or dust.
The installation site must be free from vibrations also at a distance of presses, planing
machines, etc.
The substructure must be suitable for the drilling machine. Ensure that the floor has suffi-
cient load bearing capacity and is level.
The ground must be prepared in a way that potential coolants cannot penetrate the floor.
Any parts sticking out such as stops, handles, etc. have to be secured by measures taken
by the customer if necessary in order to avoid endangering persons.
Provide sufficient space for the personnel preparing and operating the machine and trans-
porting the material.
Also make sure the machine is accessible for setting and maintenance works.
3.6

Cleaning of the machine

CAUTION!
Do not use compressed air to clean the machine.
Your new drill must be completely cleaned after it is unpacked to ensure that all moving parts
and sliding surfaces are not damaged when the machine is operated. Each unit leaves the
factory with all exposed parts and sliding surfaces suitably greased to avoid oxidation during
the time that elapses before it is placed into operation. Wipe all metallic surfaces with a clean
cotton cloth. Clean the plastic parts with cleaning agents suitable for plastic.
3.7

First commissioning

WARNING!
The machine may only be commissioned after proper installation.
If the drilling machine is initially operated by inexperienced personnel, you endanger
both people and the equipment. We do not accept any liability for damages caused by
incorrectly performed commissioning.
3.8

Warming up the machine

ATTENTION!
If the drill is immediately operated at maximum load when it is cold, it may result in
damages to the machine.
INFORMATION
To ensure a long service life of your drilling machine, we recommend that you do not exceed a
maximum rotation speed of 500 min
immediately after having transported the machine, it should be warmed up at a speed of only
500 1/min for the first 30 minutes.
Version 2.0.2 - 2022-06-28
-1
during the first hour of operation. If the drill is cold, e.g.