Z9264F-On Switch Installation; Unpack; Unpacking Steps - Dell EMC Z9264F-ON Installation Manual

Hide thumbs Also See for Z9264F-ON:
Table of Contents

Advertisement

To install the Z9264F-ON switch, complete the installation procedures in the order presented in this chapter.
Always handle the switch and components with care. Avoid dropping the switch or its field replaceable units (FRUs).
NOTE:
ESD damage can occur if components are mishandled. Always wear an ESD-preventive wrist or heel ground strap when
handling the Z9264F-ON switch and components. As with all electrical devices of this type, take all the necessary safety
precautions to prevent injury when installing this switch.
Topics:

Unpack

Ground lug assembly
Four-post rack assembly
Four-post rack mount
2RU front-rack installation
Optics installation
Switch start-up
Switch replacement
After switch placement
Unpack
NOTE:
Before unpacking the switch, inspect the container and immediately report any evidence of damage.
When unpacking the switch, ensure that the following items are included:
One Z9264F-ON switch
One RJ-45 to DB-9 female cable
Two sets of rail kits, no tools required
Two PSUs
Four fan units
Two AC power cables, country or region specific
Z9264F-ON Setup Guide
Safety and Regulatory Information
Warranty and Support Information

Unpacking steps

Unpack the switch carefully.
1
Place the container on a clean, flat surface and cut all straps securing the container.
2
Open the container or remove the container top.

Z9264F-ON switch installation

Z9264F-ON switch installation