Figure 10. Ground lug assembly attached
7
Attach the GND lug bracket assembly to your switch using the two removed screws, as shown.
Torque the M4 screws to ±8–10 in-lbs.
Figure 11. Ground lug assembly attached
8
Attach the other end of the ground wire to your rack ground point.
9
Install your switch into your rack using the

Four-post rack assembly

Due to the chassis weight, the Z9264F-ON switch does not support a two-post rack installation; you must install the switch in a four-post
rack.
To install in a four-post rack, follow the instructions in your rack frame kit. In a four-post rack, the maximum distance between the front and
back vertical posts is 36 inches (91.44 cm); the minimum distance is 24 inches (60.96 cm).
Z9264F-ON switch
installation.