4.1
Emergency operation at line module E3M111 level
4.2
Emergency operation at line module E3M080 level
4.3
General requirements
4.4
Wiring principle
B3Q700 (CPU)
'FC'
K5
K7
K6
A2/B2
A1/B1
Supply circuit 2
(Emergency supply)
Supply circuit 1
Emergency operation circuit
C-Bus return line
1)
C-Bus loop line = max. 1000m (at G51 ø 0.6mm) incl. return line or max. 1400m at G51 ø 0.8mm
Siemens Building Technologies
Fire & Security Products
Alarm evaluation in "Emergency operation" mode via Emergency operation
–
processor and "Emergency operation" in the detector
With emergency alarm a "Collective alarm" is given at the B3Q700 with the re-
–
sponse indicator in the detector flashing
With line short circuit and malfunction of the line processor no "Emergency
–
alarm" is given
Alarm evaluation with "Emergency operation" via hardware comparators
–
With emergency alarm the "Collective alarm" is given at the B3Q700 without the
–
response indicator at the detector flashing
Selectable Function "Short circuit = Alarm" also fulfilled with emergency alarm
–
At least one control console per system must comply with standard EN54, i.e. must
have Emergency operation capability and Emergency power supply.
Emergency power supply
This consists of a second supply circuit to stations located elsewhere
–
For this purpose the B3Q700 has 2 de-coupled supply inputs
–
B3Q700
'FT'
K5
K7
K6
A2/B2
A1/B1
C-Bus
1)
Two requirements must be met for control consoles located elsewhere. At least
one control console must comply with standard EN54 (i.e. have emergency opera-
tion capability and emergency supply).
EN54 requirements:
Communication as loop line
Operation also in emergency mode
Second de-coupled 24V supply
B3Q700
'FT'
K5
K7
K6
A2/B2
A1/B1
(= C-Bus designed as loop line)
(= 3 additional wires for emergency operation
between CPU and control consoles)
(= 3 additional wires if there is no autono-
mous power supply)
Emergency operation
B3Q700
'FT'
K5
K7
K6
A2/B2
A1/B1
17
007831_a_en_--.doc