Advanced Energy
Figure 5‑37. Shield clamp

dASM Commissioning

To ensure optimal functionality of the dASM grid load optimization, make sure to do
the following when commissioning:
• Check the power controller for in-phase grid connection
• Check wiring of patch cables
• Select operating mode TAKT (with the same TAKT cycle period) for all power
controller devices
• Verify these parameters on the master unit:
◦ dASM NO. OF DEVICES
◦ dASM POWER THRESHOLD [W]
• Start up each unit in the dASM group

dASM Notification

The dASM grid load optimization generates the following notifications in the master
unit in the event of an error:
• dASM device number is incorrect: Check patch cable connections/
parameter dASM device number
• dASM power limit has been exceeded: Reduce setpoints of the
assembly as appropriate
The notifications generated can be reported via:
• Fault log
• LED
• Relay
• Thyro-Touch display
• Thyro-Tool Pro PC software
57010148-00B
Shield clamp
Cable
Exposed shield
Installation, Setup, and Operation
Thyro-PX® Power Controller
5‑40

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Thyro-px seriesThyro-px 1pxThyro-px 2pxThyro-px 3px

Table of Contents