Checking Dkcps Power Supply Unit Connections - Hitachi G200 Service Manual

Virtual storage platform
Hide thumbs Also See for G200:
Table of Contents

Advertisement

4.
Hold the power supply with both hands, and then pull it gently and
remove it.
5.
Hold up the latch on the cable holder of the new power supply to release
the lock, and then slide the cable holder forward.
6.
With the lever opened completely, insert the new power supply into the
slot. Wait at least 20 seconds, and then insert the power supply all the
way into the slot. If the power supply does not install all the way into the
slot, reorient the power supply, and then reinsert it into the slot.
7.
Close the lever completely.
8.
Using a Phillips screwdriver, tighten the blue screw to secure the power
supply.
9.
Connect the power cable to the power supply, and then secure the cable
using the cable holder.
10.
Confirm that the red ALM LED is off at the power supply and the green
RDY LED is on.
If the red ALM LED does not go off after more than 30 minutes following
replacement of the power supply, remove the power supply, wait at least
30 seconds, and then reinstall it.

Checking DKCPS power supply unit connections

Procedure
1.
In the Alert Detail window of the maintenance utility, click Close.
2.
In the left pane, click Controller Chassis to check the locations of the
target power supply unit.
• CBSS/CBSL:
Replacing a power supply
Service Guide for VSP Gx00 and VSP Fx00 Models
145