Pre-Installation Verification
Verify Pre-Installation Requirements
Check Components
PN: 1725-36028-001_T.doc
Check the site to be sure pre-installation work has been completed
correctly. This includes:
Location chosen for the SpectraLink 8000 Telephony Gateway is
•
adequate and power is available.
•
APs are interoperable with SVP and coverage is adequate.
•
Telephone lines for the wireless devices are installed and properly
terminated.
•
When installing a TGA116, the grounding terminal in the rear
panel of each unit must be electrically connected to earth ground.
See Chapter 6 Install SpectraLink 8000 Telephony Gateway -
Grounding instructions.
•
Dedicated line is available for remote access to diagnostic modem.
•
Telephone system administrator is on-site to program the existing
telephone system.
The following items should be at the installation site.
SpectraLink 8000 Telephony Gateway: Depending on the size
•
of your system there may be four or more SpectraLink 8000
Telephony Gateways which will be linked together to support
additional users.
•
AC Adapter: Supplies power to the SpectraLink 8000 Telephony
Gateway.
Use only the provided Class II AC Adapter with output 24V DC, 1A.
5
29
Need help?
Do you have a question about the SpectraLink 1725-36028-001 and is the answer not in the manual?