MGC-50 Hardware Installation

Unpacking and Positioning the MGC-50

To unpack and position the MGC-50:
1.
When you receive your MGC-50, inspect the equipment for damage and
verify that the components match the packing slip. If you did not receive
a component or if there is damage to the system, notify Polycom
immediately.
Wood Packing Case
Lock in Closed Position
Lock in Open Position
Figure 2-11: MGC-50 package
2.
Place the MGC-50 unit on a stable flat surface in a location that meets
the MGC-50's environment requirements, which are:
Operating temperature: 10°–40°C (50°–104°F)
Humidity: 15%–90% noncondensing
Altitude: Up to 3,000m (10,000ft)
ESD: +8 kV