Installing the server blade into the enclosure

Installation sequence and checklist

Step
Description
1
Perform site preparation (see Site preparation on page 10 for more
information).
2
Unpack and inspect the server shipping container and then inventory the
contents using the packing slip.
3
Install additional components shipped with the server. For these procedures, see
the documentation that with the component or the user service guide.
4
Install and power on the server blade.
5
Configure iLO 3 MP access.
6
Access iLO 3 MP.
7
Access UEFI from iLO 3 MP.
8
Download latest firmware and update using HP Smart Update Manager.
9
Install and boot the OS.
NOTE:
For more information regarding HPE Integrity Server Blade upgrades, see Upgrading a conjoined
configuration on page 59 for more information.

Installing and powering on the server blade

Preparing the enclosure

HPE BladeSystem enclosures ship with device bay dividers to support half-height devices. To install a full
height device, remove the blanks and the corresponding device bay divider.
CAUTION:
To prevent improper cooling and thermal damage, do not operate the server blade or the enclosure
unless all hard drive and device bays are populated with either a component or a blank.
Procedure
1. Remove the device bay blank.
Installing the server blade into the enclosure
Completed
17

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Integrity BL860C i4 and is the answer not in the manual?