Installing The Server Blade Into The Enclosure; Installation Sequence And Checklist; Installing And Powering On The Server Blade; Preparing The Enclosure - HP Integrity BL860c i2 User's & Service Manual

Server blade
Hide thumbs Also See for Integrity BL860c i2:
Table of Contents

Advertisement

3 Installing the server blade into the enclosure

Installation sequence and checklist

Step
Description
1
Perform site preparation (see
2
Unpack and inspect the server shipping container and then inventory the contents using the
packing slip.
3
Install additional components shipped with the server.
4
Install and power on the server blade.
5
Configure iLO 3 MP access.
6
Access iLO 3 MP.
7
Access UEFI from iLO 3 MP.
8
Download latest firmware using HP Smart Update Manager
9
Install and boot the OS.
NOTE:
For more information regarding HP Integrity Server Blade upgrades, see
conjoined configuration" (page

Installing and powering on the server blade

Preparing the enclosure

HP BladeSystem enclosures ship with device bay dividers to support half-height devices. To install
a full height device, remove the blanks and the corresponding device bay divider.
CAUTION:
or the enclosure unless all hard drive and device bays are populated with either a component or
a blank.
1.
Remove the device bay blank.
"Site preparation" (page
66)for more information.
To prevent improper cooling and thermal damage, do not operate the server blade
10)for more information).
Installation sequence and checklist
Completed
"Upgrading a
15

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Integrity bl890c i2Integrity bl870c i2

Table of Contents