Testing functionality by secondary injection
11.7.1.1
146
to-phase quantities, positive sequence quantities, negative sequence quantities, maximum
quantity from the three-phase group, minimum quantity from the three-phase group,
difference between maximum and minimum quantities (unbalance) can be derived and
then used in the function.
Due to the versatile possibilities of CVGAPC itself, but also the possibilities of logic
combinations in the application configuration of outputs from more than one CVGAPC
function block, it is hardly possible to define a fully covering general commissioning test.

Built-in overcurrent feature (non-directional)

Procedure
1.
Go to Main menu/Test/Function test modes/Multipurpose protection/
GeneralCurrentVoltage(GAPC)/CVGAPC:x and make sure that CVGAPC to be
tested is unblocked and other functions that might disturb the evaluation of the test
are blocked.
2.
Connect the test set for injection of three-phase currents to the appropriate current
terminals of the IED.
3.
Inject current(s) in a way that relevant measured current (according to setting
parameter CurrentInput) is created from the test set. Increase the current(s) until the
low set stage trips and check against the set trip value.
4.
Decrease the current slowly and check the reset value.
5.
Block high set stage if the injection current will activate the high set stage when
testing the low set stage according to below.
6.
Connect a TRIP output contact to the timer.
7.
Set the current to 200% of the trip value of low set stage, switch on the current and
check the time delay.
For inverse time curves, check the trip time at a current equal to 110% of the trip
current at t_MinTripDelay.
8.
Check that TRIP and PICKUP contacts trip according to the configuration logic.
9.
Release the blocking of the high set stage and check the trip and reset value and the
time delay for the high set stage in the same way as for the low set stage.
10. Finally check that PICKUP and TRIP information is stored in the event menu.
Information on how to use the event menu is found in the operator's
manual.
1MRK 511 366-UUS -
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion670 seriesRelion 670 seriesRelion res670

Table of Contents