Section 10
Testing IED operation
10.7
88
If some setting deviates, check the analog input settings under
Main menu/Settings/General settings/Analog modules
If the IEC61850-9-2LE communication is interrupted during current
injection, the report tool in PCM600 will display the current that was
injected before the interruption.
IEC10000032 V1 EN
Figure 21:
PCM600 report tool display after communication interruption
Testing the protection functionality
Each protection function must be tested individually by secondary injection.
1MRK 511 366-UUS -
IEC10000032-1-en.vsd
Commissioning manual