ABB RES670 2.1 Commissioning Manual page 99

Phasor measurement unit
Table of Contents

Advertisement

1MRK 511 366-UUS -
Commissioning manual
1.
Right click on the IED in the plant structure and select Signal Monitoring.
2.
Click on the List View tab.
3.
Click Forcing Session in the menu IED/Start Forcing.
IEC15000023 V1 EN
4.
Click Start editing signal value for forcing on the tool bar.
IEC15000024 V1 EN
The Signal Monitoring menu changes and indicates the forcing values that can be
edited.
IEC15000025 V1 EN
5.
Select and edit the values.
6.
Click Acknowledge and send.
Section 10
Testing IED operation
93

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion670 seriesRelion 670 seriesRelion res670

Table of Contents