Figure 121: Power System Segregation Based Upon Frequency Measurements - GE MiCOM P40 Agile Technical Manual

Hide thumbs Also See for MiCOM P40 Agile:
Table of Contents

Advertisement

Chapter 11 - Frequency Protection Functions
P14D
Stage
Element
Frequency Setting (Hz)
Time Setting (Sec.)
2
Stage 6(f+t)
51.0
20
The relatively long time delays are intended to provide time for the system controls to respond and will work well in
a situation where the increase of system frequency is slow.
For situations where rapid increase of frequency is expected, the protection scheme above could be supplemented
by rate of change of frequency protection elements.
In the system shown below, the generation in the MV bus is sized according to the loads on that bus, whereas the
generators linked to the HV bus produce energy for export to utility. If the links to the grid are lost, the generation
will cause the system frequency to rise. This rate of rise could be used to isolate the MV bus from the HV system.
To utility
IPP generation
HV bus
Load
MV bus
Local generation
Load
E00857

Figure 121: Power system segregation based upon frequency measurements