Front Panel
The front panel has three sets of LED indicators, providing a visual indication
Indicators
of the operational status of the unit:
IED1 (COM 3)
IED2 (COM 4)
XCOM 1 (COM 5)
XCOM 2 (COM 6)
GE Information
Operating the D25
LED
POWER
Green: on when power supply is operating normally.
RUN
Green: on when the D25 microprocessor system is
running. With a Type III WESDAC board the RUN
LED flashes at about 2 Hz, depending on processor
load.
COMMUNICATIONS
Red: on to indicate whether and when each port is
transmitting (TX) and/or receiving (RX):
Note:
LOCAL
The D25 Plant I/O Subsystem monitors the state of
the CONTROLS switch only if a control board is
REMOTE
installed.
If the CONTROLS switch is in the REMOTE
position at startup:
green LOCAL LED lights immediately when the D25
is turned on.
green LED remains on until the D25's internal POST
diagnostics are complete.
if the diagnostics do not pass, the indicator remains
green.
After the D25 has started up normally, the indicator
should follow the state of the CONTROLS switch:
if the switch is moved to the REMOTE position, the
red REMOTE LED lights after a momentary delay,
and the LOCAL LED turns off.
Local/Remote LEDs flashing indicate one or more active
sealed-in outputs (only if a D25 High Current KE Control
Output Module is present in the D25)
Color and Function
OPERATION
XCOM indicators light only if card is
installed.
CONTROLS