Testing Hardware I/O Points,
Digital Input
Testing Digital Inputs: Digital input changes are displayed in WESMAINT.
Verification
Test
To conduct this test the code and configuration file must be downloaded to
Procedure:
the D25's FLASH memory.
Verify Digital
Input
Note:
From the WESMAINT II+ Main Menu:
Step
1
2
3
4
5
Press
Navigating
through screens
Press
Press
86
Continued
The following procedure assumes that the digital inputs for the D25
are configured to use supplied wetting. Refer to page 36 for
configuration information.
On the Main Menu, type 1 — System Data Display.
Results: The System Data Menu appears.
On the System Data Menu, type 1 — Digital Input Display.
Results: The point numbers and (optionally) point descriptions
appear on the WESMAINT II+ display.
Use the arrow keys to move up or down to highlight the desired
point number.
Use a wire jumper to short out the desired input point, and verify
that WESMAINT shows that the point status has changed to On.
Go back to Step 3 and repeat the test as necessary to test other
available digital points.
to move to the Next page.
N
to move to the Previous page.
P
to back up to the previous menu level.
ESC
994-0081-3.00-21