7.
ASSEMBLY / INSTALLATION
7.1.
Safety instructions
DANGER!
Risk of injury from high pressure in the equipment!
• Before loosening pneumatic lines and valves, turn off the pressure
and vent the lines.
Danger of explosion in explosive atmosphere
(only in the event of a fault as it is zone 2)!
• Opening the hood or the housing in an explosive atmosphere is
only allowed in a not energized state!
WARNING!
Risk of injury due to electrical shock!
• Before reaching into the system (except for the Teach-In procedure
in a non-explosive atmosphere) switch off the power supply and
secure it to prevent restarting!
• Observe applicable accident prevention and safety regulations
for electrical equipment!
Risk of injury from improper installation!
• Installation may be carried out by authorized technicians only and
with the appropriate tools!
Risk of injury from unintentional activation of the system and
an uncontrolled restart!
• Secure system from unintentional activation.
• Following assembly, ensure a controlled restart.
Type 8681
7.2.

Assembly

For the installation of the Control Head Type 8681 to a process
valve, you will require a process valve-specific hub flange as an
adapter. The hub flange must be adapted to the design of the
process valve.
Mount the piston rod with the target on the process valve spindle.
Observe reference dimensions!
Fasten the hub flange on the process valve. During this, observe
central alignment and sealing conditions!
Check the secure fit of the sealing rings (in the upper and lower
grooves).
Mount the control head on the hub flange (seamlessly 360°
rotatable).
Secure the control head with the two locking screws (shoulder
screws M5, tightening torque: max. 3.2 Nm) in the middle grove
of the hub flange (see operating instructions).
7.3.
Pneumatic Installation
Connect the required working connections 2/A1 to 2/A3 (each
according to model) with the corresponding connections on the
process valve.
Connect the supply line to supply pressure connection 1/P (2.5
to 8 bar).
A silencer has already been mounted on the Exhaust Air Connection
(3/R) in the supplied state.