Important
6. Verify that the startup procedure has started by checking the following:
◦ Status LED Ready is continuously lit.
◦ Status LED ON flashes.
☞
Important
In normal operating circumstances, the startup procedure takes approximately five
minutes. For the initial startup, this procedure may take longer.
NORMAL START UP
WARNING:
Before turning on the inverter, ensure that the connection box cover is
properly installed.
AVERTISSEMENT:
Avant d'allumer l'onduleur, s'assurer que le couvercle de la boîte de jonction
est bien installé.
WARNING:
Maintenance personnel must receive proper training before installing,
troubleshooting, or maintaining high-energy electrical equipment. Potentially
lethal voltages could cause death, serious personal injury, or damage to the
equipment. Ensure that all appropriate safety precautions are taken.
AVERTISSEMENT:
Le personnel d'entretien doit recevoir une formation appropriée avant
d'installer, de dépanner ou d'entretenir un équipement électrique à haute
énergie. Des tensions potentiellement mortelles pourraient provoquer la
mort, des blessures graves ou des dommages à l'équipement. S'assurer que
toutes les consignes de sécurité appropriées ont été respectées.
570-1003552-05A
The inverter automatically performs a self-test after completion of the
initialization routine. The individual system components are checked and
data is imported from the power control board (PCB). If there is a fault,
the type of fault will indicate what corrective measures have to be taken.
When the solar array voltage is greater than 200 V, the startup procedure
starts.
Advanced Energy® AE 3TL Inverters
Operating
5‑3