Advanced Energy AE 3TL 600 Series Installation And Operation Manual page 63

Table of Contents

Advertisement

4. Connect the remaining grid-side conductors to the L1, L2, L3, and N locations
on the AC terminal block
5. Tighten each AC input terminal and torque each terminal clockwise to a value
between 1.2 Nm (10.6 lb-in) and 1.5 Nm (13.0 lb-in).
6. Turn on the utility circuit breaker.
7. Using a multimeter, confirm the AC voltage measurement coming from the
utility. The utility line is routed to the feedthrough installed on the bottom of
the inverter.
The maximum is 304.7 V (phase to neutral conductor). If the AC voltage is
higher, contact your local utility company.
8. Confirm that the feed-in AC utility voltage meets the requirements of the
power system using a multimeter by measuring the AC voltage between line
and ground.
9. Turn off the utility grid circuit breaker.
10. Complete a final check of the connections to ensure they are snug and
protected from rain.
11. Close the connection box cover.
570-1003552-05A
Advanced Energy® AE 3TL Inverters
Installing
4‑27

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ae 3tl 1000 series

Table of Contents