The next step in the assembly process is to install the
burner door and draft diverter. The pre-assembled boiler
comes with these components already installed.
7.9.1

Positioning the draft diverter

The GP sealant rope (fiberglass cord with silicon casing)
which forms a seal is inserted in the draft diverter at the
factory.
B Glue GP sealant rope (approx. 59 1/16 inches
(1500 mm) long) into the groove on the rear section
using adhesive.
B Insert the sealant rope in such a way that its joint is at
the top of the groove.
B Place the draft diverter onto the four threaded studs on
the rear section and secure using washers and nuts.
6
5
Fig. 28 Positioning the draft diverter
1
Sealant rope joint at the top of the groove
2
Sealant rope
3
Draft diverter
4
Threaded studs
5
Rear section
6
Threaded studs
28
7.9.2
Fig. 29 shows the fully equipped rear section with the
cleanout covers on the draft diverter and the cleanout
covers on the rear section.
B GP10Glue GP sealant rope (approx. 31 1/2 inches
(800 mm) long) into the groove on the rear section with
Silastic adhesive (sealant rope joint at top).
B Secure the cleanout covers on the rear section with
washers and nuts.
1
1
2
4
3
Fig. 29 Securing the cleanout covers
1
Cleanout cover on the draft diverter
2
Cleanout cover on the draft diverter
3
Cleanout cover on the rear section
4
Cleanout cover on the rear section
6 720 6 2 625-25.1o

Screwing cleanout cover onto rear section

Logano G615 - Subject to technical modifications
3
6 7 0 64 6 5- 6.1o

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents