Commissioning The System; Start Up The Control Panel; Initial Burner Start-Up - Buderus Logano G615 Installation And Service Instructions Manual

Low-temperature oil/gas boiler boilers for oil/gas-fired power burners
Table of Contents

Advertisement

11
System start-up

11.2 Commissioning the system

B For commissioning, establish the required normal
operating pressure.
B Check that the flue gas baffles have been inserted
correctly.
Details about the quality of the boiler water
operator's log
NOTICE: Boiler damage due to temperature
stresses.
If you fill the heating system when it is hot, the
resulting temperature stress can cause
stress cracks causing the boiler to leak. The
boiler will then leak.
B Only fill the heating system when cold.
(max. supply temperature 104 °F (40 °C)).
B During operation, only fill the heating
system via the fill valve on the system side.
Fig. 57 Checking that flue gas baffles are seated
correctly

11.3 Start up the control panel

Please see the accompanying technical documentation
for the 4000 series control panel for information about on
how to start it up.
44

11.4 Initial burner start-up

B When commissioning the burner, follow the
instructions in the technical documentation enclosed
with the burner.
B Complete the commissioning log for the burner.
720 42 25-49.1o
Logano G615 - Subject to technical modifications