6.20 Checking For Leaks During Operation; 6.21 Fitting Sections Of The Casing; Informing The User; Handing Over Technical; Documentation - Buderus Logano plus GB312 Installation And Maintenance Instructions Manual

Gas condensing boiler
Table of Contents

Advertisement

6
Commissioning
Country
Gas type
AT, BA, BE, BG,
Natural gas H
BY, CH, CN, CZ,
(G20) or
DE, DK, EE, ES,
Natural gas L
GB, GR, HR, IE,
(G25)
IT, LU, PL, PT,
Natural gas
RO, RU, SI, SK,
L
(formerly
W
UA
GZ41.5)
Natural gas L
NL
(G25)
Natural gas H
(G20)
HU
Natural gas S
(G25.1)
Tab. 17 Gas types and supply pressures
1) The gas supply utility must assure the minimum and maximum
pressures (in accordance with the national requirements for gas
supply utilities).

6.20 Checking for leaks during operation

B With the burner operational, use a foaming agent to
test all sealed points in the entire burner gas train, such
as:
• Pressure test nipple
• Plug for gas supply pressure
• Fittings (also at the gas connection) etc.
The agent must be approved for gas tightness testing.
NOTICE: Risk of system damage due to
short circuit!
B Prior to checking for leaks, cover areas at
risk, e.g. the internal water pressure
sensor and the return temperature sensor
in the boiler return.
B Never spray leak detection agent onto
cable entries, plugs or electrical cables.
Do not allow it to drip onto them either.
B To prevent corrosion, carefully wipe off the
leak detection agent afterwards.

6.21 Fitting sections of the casing

If the side and front panels cannot be fitted
correctly, plumb the boiler vertically
(
Chapter 5.9, page 27)
B First hook in side panels [2] at the bottom, then lift them
slightly and hook in at the top.
B Secure the side panels with locking screws [3] at the
front and back of the boiler.
B First hook in the bottom of the front panel [1], then raise
slightly and hook in at the top.
40
1)
Gas supply pressure
[mbar]
Min.
Rated
Max.
17
20
25
20
25
30
20
25
33
B Secure the front panel with locking screw [3] at the top
of the boiler.
Fig. 44 Fitting sections of the casing
1
Front panel
2
Side panel
3
Locking screws
B Affix the clear pocket containing the technical
documentation in a clearly visible spot on the side of
the boiler.
6.22 Informing the user; handing over
technical documentation
B Make the user familiar with the heating system and the
boiler operation.
B Make the user aware that the boiler and control unit
must only be opened by qualified contractors.
B Confirm commissioning in the report
(
Chapter 6.23).
B Together with the user, carry out a system shutdown
and restart.
B Explain to the customer what to do in an emergency,
e.g. a fire, referring to the operating instructions.
B Hand over the technical documentation to the user.
Logano plus GB312 - Subject to technical modifications.

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents