Ptx5000 Clearance Requirements For Airflow And Hardware Maintenance; Figure 30: Chassis Dimensions And Clearance Requirements - Juniper PTX Series Hardware Manual

Packet transport switch
Hide thumbs Also See for PTX Series:
Table of Contents

Advertisement

PTX5000 Clearance Requirements for Airflow and Hardware Maintenance

Related
Documentation
Copyright © 2012, Juniper Networks, Inc.
When planning the installation site, allow sufficient clearance around the rack (see
30 on page
59):
For the cooling system to function properly, the airflow around the chassis must be
unrestricted.
NOTE:
If you mount the chassis in a cabinet, be sure that ventilation is
sufficient to prevent overheating.
For service personnel to remove and install hardware components, there must be
adequate space at the front and back of the chassis. At least 24 in. (61.0 cm) are
required both in front of and behind the packet transport switch. NEBS GR-63
recommends that you allow at least 30 in. (72.6 cm) behind the rack.
Additional clearance is required to accommodate the depth of the cable management
system: 3.8 in. (9.7 cm) additional depth in the front of the chassis.

Figure 30: Chassis Dimensions and Clearance Requirements

30" (72.6 cm)
clearance recommended
for maintenance
Front
19"
(48.3 cm)
(mounting hole width)
Front
Cable management system
depth 3.8" (9.7 cm)
PTX5000 Chassis Description on page 12
PTX5000 Cooling System Description on page 18
Maintaining the PTX5000 Air Filters on page 109
Maintaining the PTX5000 Fan Trays on page 110
PTX5000 Physical Specifications on page 255
PTX5000 Installation Safety Guidelines on page 225
Maintenance and Operational Safety Warnings for Juniper Networks Devices on page 234
Chapter 5: Preparing for PTX5000 Packet Transport Switch Installation
33" (83.3 cm)
Center-mounting bracket
Front-mounting flange
Figure
30" (72.6 cm)
clearance recommended
for maintenance
Rear
17.43"
(44.3 cm)