Electrical installation
4.6 Connections
4.6.12.5
Cable routing for Active Line Modules
For the Active Line Modules, the customer must carry out the following cabling or connection
work:
Table 4- 17
Cable routing
PROFIBUS cable or PROFINET cable to the Control Unit
DRIVE-CLiQ connections / signal cables to the Control Unit
Signal cables to the customer terminal block –X55
Notice:
The "Basic rules for cable routing" and "Preparatory steps" described above must
be observed whenever any cabling or connection work is performed!
120
Checklist for cabling or connection work for Active Line Modules
Completed?
Cabinet Modules
Manual, 03/2013, A5E03263538A