3.8

First commissioning vector control AC drive blocksize format

An example provided in this chapter explains all the configuration and parameter settings, as
well as tests that are required for initial commissioning. Commissioning is carried out using
the STARTER commissioning tool.
Preconditions for commissioning
● The commissioning preconditions (Page 30) have been met.
● The commissioning checklists (Page 32) (Tables 2-1 and 2-2) have been completed and
the points fulfilled.
● The STARTER commissioning tool is installed and activated.
– System prerequisites, refer to the Readme file in the STARTER installation directory.
● The drive system has been wired according to the specifications.
● The communication between the PG/PC and drive system has been prepared.
● The power supply of the Control Unit (24 V DC) has been switched on.
3.8.1

Task

A drive unit is to be commissioned (vector control, closed-loop speed control), without
DRIVE-CLiQ and without speed encoder with the following components:
Designation
Closed-loop control
Control Unit
Operator Panel
Infeed and drive
Power Module
Motor
Commissioning is performed using the BOP20.
The function keys on the BOP20 must be parameterized so that the ON/OFF signal and
speed settings can be defined via these keys.
STARTER Commissioning Manual
Commissioning Manual, (IH1), 07/2016, 6SL3097-4AF00-0BP5
3.8 First commissioning vector control AC drive blocksize format
Component
Control Unit 310-2 DP
Basic Operator Panel BOP20
240-2 Power Module
Induction motor
(without DRIVE-CLiQ interface)
Commissioning
Article number
6SL3040-1LA00-0AA0
6SL3055-0AA00-4BA.
6SL3210-1P...-....
1LA7
155

Advertisement

Table of Contents
loading

Table of Contents