Notes On Commissioning; Recommended Order For First Commissioning - Siemens SIMOTION Series Commissioning And Hardware Installation Manual

Hide thumbs Also See for SIMOTION Series:
Table of Contents

Advertisement

Commissioning (software)

10.5 Recommended order for first commissioning

See also
Connection requirements (Page 99)
Parameter assignment / addressing requirements (Page 127)
10.4

Notes on commissioning

Starting up communications
The following components must be commissioned:
● SIMOTION P320-4
● PROFINET component
Commissioning is performed either via the programming device or by installing the software
required for commissioning on the SIMOTION P320-4.
If a panel is used, it must be connected.
Commissioning the components
Please refer to the relevant documentation for the commissioning of the components used
with SIMOTION P320-4:
● ET 200 PN I/O
● PROFINET IO drives,
10.5
Recommended order for first commissioning
The individual steps for first commissioning are listed below in the recommended order.
1. The complete system is connected mechanically and electrically, and has been verified.
– SIMOTION P320‑4
– Drives
– Motors
– SIMATIC S7 I/O components
– HMI user interfaces
2. The article numbers of the drives and SIMATIC S7 I/O components should be available.
You need these order numbers when setting up a SIMOTION project to verify that the
components selected from the hardware catalog in the HW Config application correspond
to the ones used in the system.
3. Prepare the drives for communication on the PROFINET IO.
4. Commission the drives via PROFINET IO.
Literature: Function description of the associated drives
154
SIMOTION P320-4 E / P320-4 S
Commissioning and Hardware Installation Manual, 11/2016