Alcatel-Lucent 1645 AMC Installation Manual page 109

Access multiplexer compact amc
Hide thumbs Also See for 1645 AMC:
Table of Contents

Advertisement

Powering
...................................................................................................................................................................................................................................
Switching on and testing supply voltage
Overview
This section describes the procedure for powering the system. Please observe the order of
steps described below.
Procedure
Proceed as follows to switch on and test the power supply:
...................................................................................................................................................................................................
Check the voltage at the external Battery Distribution and Fuse Bay (BDFB) or at the
1
Power Distribution Panel (if available) and enter the measured value in the result table
(see chapter 9,
Result:
DC power supply: –18 V ... – 72 V
AC power supply: 90 V ... 264 V.
...................................................................................................................................................................................................
Switch off the power.
2
...................................................................................................................................................................................................
Connect the power cable between the power interface of the 1645 AMC unit and the
3
BDFB (or PDP).
ote: If an AC/DC converter is used, it has to be connected to the DC connector of
the 1645 AMC unit first and then to the BDFB (or PDP).
...................................................................................................................................................................................................
Connect the fan power cable between the power interface of the fan unit and the BDFB
4
(or PDP).
...................................................................................................................................................................................................
Switch on the power.
5
...................................................................................................................................................................................................
6
Check that the green "Power" LED of the 1645 AMC unit is illuminating.
E
N D
O F
...................................................................................................................................................................................................
Power failure
If the powering procedure described above was unsuccessful, please refer to Appendix A,
section
...................................................................................................................................................................................................................................
365-313-103R8.0
Issue 2 July 2009
"Power supply measurements" (p.
The voltage must be in the range as given below.
ote: Do not proceed if the voltage is outside the range.
S T E P S
"Power failure" (p.
B-2).
Alcatel-Lucent – Internal
Proprietary – Use pursuant to Company instruction
Switching on and testing supply voltage
9-1)).
Power initialization
5-3

Advertisement

Table of Contents
loading

Table of Contents